Background

Since its incorporation, Blueskype is deploying over 40MWp of high-performance solar PV systems on bi-facial panels, with a pipeline of over 700MW across the following Provinces, Northwest, Freestate, Limpopo and inclusive of 140 MW of Wind energy in Western Cape.

Date: 21/02/2023
Blueskype Internal Lead:

CATEGORYRESPONSECOMMENTS/ACTION STEP 
ProvinceNorthwest300 MW
LocationNorthwest 
Technology Required (gas, LPG, solar, hydro)PV Solar 
Land Available (Area/Location)200 hectare + 184 hectaresLease to buy agreement signed.
Project Capacity (KWP/MW)300 MW in totalCEL stage
Current Sponsor / PartnerNoneLooking for sponsor
Off-takerPublic Client + PrivateDraft PPA stage
Relationship with off-takerClient 
Public / PrivatePublic and Private 
PPA in place (yes, no, draft)DraftNegotiations advanced and in final stage
Contact PersonN/A 
Industry / SectorGovernment And Private 
Estimated Financial RequirementsTBA 
Type of Funding Required(Debt/Equity, etc)Equity/Private FundingWe are looking for one: Using self funding model currently
Project Timelines12 months – 16 monthsIncluding construction phase
Estimated First Power (COD)2024We envisage that we should be ready with all permits end of April.
Internal Project Due Diligence Completed (Y/N)Yes All risk and due Diligence done on land
Key Permitting Requirements Completed, etc.EIA preliminary desktop assessment done EIA lodged

Date: 21/02/2023
Blueskype Internal Lead:

CATEGORYRESPONSECOMMENTS/ACTION STEP 
ProvinceFreestate400 MW Application
LocationFreestate
Technology Required (gas, LPG, solar, hydro)PV Solar 
Land Available (Area/Location)250 hectares + 350 hectaresLease to buy agreement signed.
Project Capacity (KWP/MW)400 MW in totalCEL stage
Current Sponsor / PartnerNoneLooking for sponsor
Off-takerConfidentialNegotiations in final stage
Relationship with off-takerClient 
Public / PrivatePublic and Private 
PPA in place (yes, no, draft)Draft
Contact PersonN/A 
Industry / SectorPrivate Clients 
Estimated Financial RequirementsTBA 
Type of Funding Required(Debt/Equity, etc)Private Equity + DebtWe are looking for one: Using self funding model currently
Project Timelines12 months – 16 monthsInclusive of Construction Phase
Estimated First Power (COD)2024We envisage that we should be ready with all permits end of April.
Internal Project Due Diligence Completed (Y/N)YesAll risk and due Diligence done on land
Key Permitting Requirements Completed, etc.EIA doneTown planning special consent done.

Date: 21/02/2023
Blueskype Internal Lead:

CATEGORYRESPONSECOMMENTS/ACTION STEP 
ProvinceLimpopo40 + 60 + 300 + 200 + = 600 MW
LocationLimpopo
Technology Required (gas, LPG, solar, hydro)PV Solar 
Land Available (Area/Location)900 + 200 + 430 hectaresLease to buy agreement signed.
Project Capacity (KWP/MW)600 MW in totalCEL and Budget Quote stage
Current Sponsor / PartnerNoneLooking for sponsor
Off-takerPrivate and Public clients
Relationship with off-takerClient 
Public / PrivatePublic and Private 
PPA in place (yes, no, draft)Draft
Contact Person
 
Industry / SectorGovernment And Private 
Estimated Financial RequirementsTBA 
Type of Funding Required(Debt/Equity, etc)Private Equity Fund + DebtWe are looking for one: Using self funding model currently
Project Timelines12 months – 16 monthsIncluding construction phase
Estimated First Power (COD)2024We envisage that we should be ready with all permits end of April.
Internal Project Due Diligence Completed (Y/N)Yes All risk and due Diligence done on land
Key Permitting Requirements Completed, etc.EIA done EIA lodged